1. Help Center
  2. Engineered Systems
  3. Factory Acceptance Tests (FATs)

When is the best time to schedule an FAT?

Times can vary depending on the complexity of the system and the corresponding FAT, but they are typically scheduled 2-4 weeks prior to the ship date to help maintain on-time delivery. The duration of the FAT can be anywhere from one day up to a couple of weeks.